‘Build build build’: How will the Business and Planning Bill help developers?


Last week, Boris Johnson announced his ‘new deal’, the central point of which is to build back better, greener and faster. The focus of his announcement was on future construction. What will happen to those planning permissions that have already been secured but which are due to expire in coming months? Do you need to take action to extend the life of your planning permission?

How long does a planning permission last?

Ordinarily, a planning permission will require development to commence within 3 years of the grant of planning permission. This could cause problems for anyone with the benefit of planning permission who, owing to government restrictions on site working, and then limited availability of builders and materials, has not been able to keep their permission ‘live’ by starting development. If the planning permission was granted, for example, on 3 June 2017 it would ordinarily expire on 2 June 2020 if no work on site had started. Under normal circumstances, such a planning permission would have expired.

How does the government intend to address this?

The Business and Planning Bill is currently making its way through Parliament. This, if enacted in its current form, will provide for an automatic extension for planning permissions that require development to be started no later than a date between (i) the date on which the provisions of the Act come into force (not yet known); and (ii) 31 December 2020. So, if, for example, your permission required development to begin by 1 November 2020, this date will be extended to 1 April 2021.

This doesn’t help with permissions that were due to expire before the date on which the new legislation comes into force (such as the example of 2 June 2020 above). In those cases, a person with an interest in the land can, up until 31 December 2020, apply for an ‘additional environmental approval’. The local planning authority (LPA) has 28 days to respond, saying whether or not the additional environmental approval is granted. The LPA must grant the additional environmental approval if the EIA requirement and the habitats requirement are both met.

  • The EIA requirement will be satisfied if either the development is not an EIA development, or, if it is, a reasoned conclusion was reached and included within the planning permission, as required by the Town and Country Planning (Environmental Impact Assessment) Regulations 2017.
  • The habitats requirement will be met if an assessment would not have been required, or, if it would have been required, it was undertaken prior to the planning permission being granted and the LPA is satisfied that the assessment remains up to date.

If the LPA does not respond within 28 days, they are deemed to have granted the additional environmental approval. If an additional environmental approval is granted, an extension can be granted so that development must begin by 1 April 2021.

What about outline planning permission?

The Bill contains provisions to automatically extend the deadline for applications for approval of reserved matters that should have been made between 23 March 2020 and 31 December 2021. The new deadline will be 1 April 2021.

Is there an extension for works to listed buildings?

As with planning permissions, the date for starting work under a listed building consent is extended. If works should have been commenced between 23 March 2020 and 31 December 2021, there is an automatic extension to 1 April 2021.

Is there anything to assist in getting developments built quicker?

As work on sites was halted for a period from 23 March 2020, and current social distancing measures may restrict the number of workers who can be on site at any one time, there is concern that sites are going to take longer than expected to be built out. The Business and Planning Bill allows a person with an interest in the land to apply for a modification to the terms of a planning permission. This can be to allow work on site for longer hours or for days (or parts of days) when work would not otherwise be permitted.

An application must be made to the LPA, who can agree, disagree or modify the proposal. If the LPA does not respond within 14 days, the planning permission will be deemed to have been modified as requested.

The Bill should assist those who have already obtained planning permission not to lose the benefit of them. However, if the planning permission should have expired between 23 March and the date on which the legislation comes into force, the extension will not be automatic – an application must be made.

LPAs should note the timescales for responding and put measures in place to ensure that applications are dealt with swiftly. If they fail to do so, they are at risk of being deemed to have given consent.

TLT has extensive experience in advising on all aspects of planning and environmental law. If you would like to discuss your matter, please get in touch.

Contributor: Alexandra Holsgrove Jones

This publication is intended for general guidance and represents our understanding of the relevant law and practice as at July 2020. Specific advice should be sought for specific cases. For more information see our terms & conditions


Related insights & events

View all

Hot topics

Sign up for legal insights

Sign up to receive legal insights and event/webinar invitations on the topics that interest you

Related services